Question: The Contractor submits its application for payment to the Project Manager. The application includes an amount for additional work done which was instructed by the
The Contractor submits its application for payment to the Project Manager. The application includes an amount for additional work done which was instructed by the Project Manager as a change to the Scope. There are no items in the Bill of Quantities which cover the additional work. The Project Manager notified the change as a compensation event and the Contractor has submitted its quotation for changed Prices but the Project Manager has not yet notified its acceptance.
Which TWO of the following options best describe the actions now required of the Project Manager?
Select TWO options
Instruct the Contractor to resubmit its application for payment to excluding the amount assessed for the additional work
Prepare and issue the payment certificate within one week of the assessment date
Assess the Price for Work Done to Date without taking into account the additional work under the compensation event
Include the amount in the Contractor's application for the additional work done in the assessment of the amount due
Prepare and issue the payment certificate within one week of the Contractor's application for payment
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock