The controller for VP Leni Machining has established the following overhead cost pools and cost drivers:

Overhead Cost Pool

Budgeted Overhead Cost

Cost Driver

Machine set up

240,000

Number of setups

Material handling

90,000

Units of raw material

Quality control inspection

48,000

Number of inspections

Other overhead costs

160,000

Machine hours

Total

538,000

Overhead Cost Pool

Budgeted Level for Cost Driver

Machine set up

200 setups

Material handling

60,000 units

Quality control inspection

1,200 inspections

Other overhead costs

20,000 machine hours

Order No. 1214 and 1215 have the following production requirements:

1214

1215

Machine setups

9

10

Raw materials

11,200 units

12,000 units

Inspections

160

180

Machine hours

1,950

3,000

Direct materials per unit

P12

P15

Direct labor

P159,000

P189,000

Required:

  1. Compute the total overhead of Order No 1214 and 1215 using the activity-based costing.
  2. Compute for the total manufacturing cost of No 1214 and 1215 using the activity-based costing.
  3. Supposed VP Leni uses a traditional costing, predetermines rate based on machine hours, compute the total manufacturing cost of order No 1214 and No 1215

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!