Question: The correct MRP table for item C should be Item: C Date Gross Requirements Scheduled Receipts On Hand Net Requirements Planned Order Release Item:
The correct MRP table for item C should be Item: C Date Gross Requirements Scheduled Receipts On Hand Net Requirements Planned Order Release Item: C Date Gross Requirements Scheduled Receipts On Hand Net Requirements Planned Order Release Item: C Date Gross Requirements Scheduled Receipts On Hand Net Requirements Planned Order Release Item: C Date Gross Requirements Scheduled Receipts On Hand Net Requirements Planned Order Release None of the above. Lead Time: 2 Weeks 1 2 3 4 5 6 7 8 9 135 0 135 0 135 0 Lead Time: 2 Weeks 1 2 3 4 5 6 7 8 9 135 0 135 0 135 0 Lead Time: 2 Weeks 1 2 3 4 5 6 7 8 9 135 0 135 135 0 Lead Time: 2 Weeks 1 2 3 4 5 6 7 8 9 135 0 135 0 135 0