Question: The cost associated with reducing the project schedule is known as ______. A. normal point B. crash limit C. optimal cost D. marginal cost of
The cost associated with reducing the project schedule is known as ______.
| A. | normal point | |
| B. | crash limit | |
| C. | optimal cost | |
| D. | marginal cost of compression |