Question: The cost variance for a project is calculated by Multiple Choice O EV - AC. O AC - SV. O PV - EV. O CV

The cost variance for a project is calculated by Multiple Choice O EV - AC. O AC - SV. O PV - EV. O CV - EV. O EV - PV