Question: The costs incurred during the project to develop a quality product and avoid failures are known as: Los ostos incurr dos durante el proyecto para
The costs incurred during the project to develop a quality product and avoid failures are known as:
Los ostos incurrdos durante el proyecto para desarrollar un producto de calidad y evitar fallos se conocen como:
Select the correct response:
Internal Costs
Evaluation costs
Prevention costs
External Costs