Question: The CPM estimate for a project is 5 0 days. It follows that Group of answer choices at least one path in the project network

The CPM estimate for a project is 50 days. It follows that
Group of answer choices
at least one path in the project network has a length of 49 days.
exactly one path in the project network has a length of 50 days.
at least one path in the project network has a length of 50 days.