Question: The CPM estimate for a project is 50 days. It follows that at least one path in the project network has a length of 50

The CPM estimate for a project is 50 days. It follows that at least one path in the project network has a length of 50 days. exactly one path in the project network has a length of 50 days. O at least one path in the project network has a length of 49 days