Question: The CPM method has two time estimates for each activity. The CPM Method with a single time estimate for each activity is also called PERT.

The CPM method has two time estimates for each

The CPM method has two time estimates for each activity. The CPM Method with a single time estimate for each activity is also called PERT. PERT is a probabilistic scheduling method. The CPM and PERT methods are similar to each other. Question 8 Retaken Activity E is succeeded by Activity F and Activity G. What is the LS time for Activity E