Question: The CPM model for a project returns the following slack times. Based on this information, what activities are on the critical path? Activity M N
The CPM model for a project returns the following slack times. Based on this information, what activities are on the critical path?
| Activity | M | N | P | R | S | T | U |
| Slack | 0 | 0 | 4 | 5 | 1 | 0 | 2 |
The activities on the critical path are:
M,N,T
All of the activities must be completed so all the activities are on the critical path
P,R,S,U
S,U