Question: The CPM model for a project returns the following slack times. Based on this information select the correct response. Activity M N P R S

The CPM model for a project returns the following slack times. Based on this information select the correct response.

Activity M N P R S T U
Slack 3 7 0 2 0 0 4

Crashing P two units of time will decrease the project completion time

To decrease the project completion time you must crash M,N,R, and U

Failure to crash P and S will increase the project completion time

Crashing S will not decrease the project completion time