Question: The CPM model for a project returns the following slack times. Based on this information select the correct response. Activity M N P R S
The CPM model for a project returns the following slack times. Based on this information select the correct response.
| Activity | M | N | P | R | S | T | U |
| Slack | 3 | 7 | 0 | 2 | 0 | 0 | 4 |
Crashing P two units of time will decrease the project completion time
To decrease the project completion time you must crash M,N,R, and U
Failure to crash P and S will increase the project completion time
Crashing S will not decrease the project completion time