Question: The Critical Path _ _ _ _ _ _ _ Contains constraints such as hard start & end dates Is the final path to crash

The Critical Path _______
Contains constraints such as hard start & end dates
Is the final path to crash when fast-tracking a project
Does not factor into the concept of float or slack
Is the longest path in the network with shortest project duration
Only maps a path using the lowest level in the WBS