Question: The critical path for the network activities shown below is with duration begin{tabular}{ccc} hline Activity & Duration & Immediate Predecessors hline A & 10

The critical path for the network activities

The critical path for the network activities shown below is with duration \begin{tabular}{ccc} \hline Activity & Duration & Immediate Predecessors \\ \hline A & 10 & \\ B & 8 & \\ C & 4 & A \\ D & 2 & A \\ E & 6 & B, C, D \\ \hline \end{tabular}