Question: The critical path for the network activities shown below is ____ with duration Immediate Predecessors Activity A Duration 4 B 6 A 7 D 4

The critical path for the network activities

The critical path for the network activities shown below is ____ with duration Immediate Predecessors Activity A Duration 4 B 6 A 7 D 4 A E 5 B.C,D O A-B-C-D-E: 22 O A-B-E: 15 O C-E: 12 O A-D-E: 13 O A-B-E: 11