Question: The critical path for the network shown is: Select one: O i. 1-2-4-7 O ii. 1-3-4-7 iii. 1-2-5-7 iv. 1-3-6-7

The critical path for the network shown is:
The critical path for the network shown is: Select one: O i. 1-2-4-7 O ii. 1-3-4-7 iii. 1-2-5-7 iv. 1-3-6-7