Question: The critical path for the project shown below is with duration of Activity Immediate Predecessors Time 4 A B D E None A None A

The critical path for the project shown below is

The critical path for the project shown below is with duration of Activity Immediate Predecessors Time 4 A B D E None A None A B, C, D 2 7 4 5 Select one: O a. A-B-E; 11 O b. A-B-C-D-E: 22 O c. A-B-D:10 O d. C-E; 12 O e. A-D-E; 13