Question: The critical path for this network is A - E - F and the project completion time is 22 weeks. Immediate Normal 13 Crash Normal

The critical path for this network is A - E - F
The critical path for this network is A - E - F and the project completion time is 22 weeks. Immediate Normal 13 Crash Normal Crash Activity Predecessor(s) Time Time Cost Cost 12 8 8,000 12,000 +105 ,000 7,500 0 8 0 m w THE 3 10,000 6,000 5,000 ,000 5,000 10,000 8,000 7,000 12,000 8,000 o B. D 5 9 o CA 8 If a deadline of 17 weeks is imposed, give the linear programming model for the crashing decision. Do NOT attempt to solve the problem. All that is required is the linear programming model