Question: The critical path in a CPM analysis is important because: q , q , A . more activities lie along the critical path than along
The critical path in a CPM analysis is important because:
A more activities lie along the critical path than along any other path
B the "heavy construction" activities lie along the critical path
C any delays along the critical path will delay the completion of the project
D the critical path contains the highest cost activities