Question: The Critical Path Method ( CPM ) allows us to investigate the effects of uncertainty of activity times on the project completion time. Question 5

The Critical Path Method (CPM) allows us to investigate the effects of uncertainty of activity times on the project completion time.
Question 52 options:
TrueFalse
Path A-B-C-H will take 16 days.
Path A-D-E-H will take 22 days.
Path A-F-G-H will take 30 days.
In the given scenario, which of the following statements is true?
Question 51 options:
The expected duration of the project is 68 days.
Activities B, D, and F have an earliest starting time of 0.
Path A-D-E-H has the largest slack time.
Path A-F-G-H is the critical path.