Question: The critical path of a project includes activities b, e, and f. We know that the stand deviations of these activities are 2, 5, and
The critical path of a project includes activities b, e, and f. We know that the stand deviations of these activities are 2, 5, and 2, respectively. The critical time of the project is 43. All units are day. If the PM has promised to complete the project in 52 days, what are the chances (probability) of meeting that deadline?
97%
89%
94%
80%