Question: The data in the table below represent time study observations for a woodworking operation. OBSERVATIONS ( minutes per cycle ) Performance Rating 1 1 0

The data in the table below represent time study observations for a woodworking operation. OBSERVATIONS (minutes per cycle) Performance Rating 110%115105 Element 12361.1511.200.830.5821.170.870.5331.160.780.5241.220.820.5951.240.850.600.54 Click here for the Excel Data File a. Based on the observations, determine the standard time for the operation, assuming an allowance of 15 percent of job time. (Round your intermediate calculations and final answers to 3 decimal places.) X Answer is complete but not entirely correct. Element Standard time 11.50521.206 X 30.676