Question: The data in the table below represent time study observations for element 2 of a woodworking operation. OBSERVATIONS ( minutes per cycle ) Element Performance

The data in the table below represent time study observations for element 2 of a woodworking operation.
OBSERVATIONS (minutes per cycle)
Element
Performance
Rating
1
2
3
4
5
6
2
115
0.83
0.87
0.78
0.82
0.85
1.32*
* Unusual delay, disregard observation
Based on the observations, determine the standard time for element 2 of the operation, assuming an allowance of 15 percent of job time. (Round your intermediate calculations and final answers to 3 decimal places.)