Question: The debits to Work in Process - Assembly Department for April, together with data concerning production, are as follows: April 1 , work in process:

The debits to Work in Process-Assembly Department for April, together with data concerning production, are as follows:
April 1, work in process:
Materials cost, 3,000 units
Conversion costs, 3,000 units, 40% completed
8,677
5,981
27,101
30,178
Materials added during April, 10,000 units
Conversion costs during April
Goods finished during April, 12,000 units
April 30 work in process, 1,000 units, 40% completed
All direct materials are added at the beginning of the process, and the first-in, first-out cost flow method is used.
The conversion cost per equivalent unit for April is
a. $2.69
b. $3.02
c. $2.62
d. $2.32
 The debits to Work in Process-Assembly Department for April, together with

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!