Question: The debits to Work in Process - Assembly Department for April, together with data concerning production, are as follows: April 1, work in process: Materials

The debits to Work in Process - Assembly Department for April, together with data concerning production, are as follows:

April 1, work in process:
Materials cost, 3,000 units $8,519
Conversion costs, 3,000 units,
2/3 completed $5,343
Materials added during April, 10,000 units $26,929
Conversion costs during April $30,493
Goods finished during April, 11,500 units - - -
April 30 work in process, 1,500 units,
1/2 completed - - -

All direct materials are placed in process at the beginning of the process and the average cost method is used to cost inventories. What is the cost of the work in process inventory on April 30?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!