Question: The decision whether single or multiple prime contracts should be used on a project should be made: 1. On bid day 2. When contracts are

The decision whether single or multiple prime contracts should be used on a project should be made:

1.

On bid day

2.

When contracts are signed

3.

In the early stages of project development

4.

When the budget is determined for the project