Question: The demand cor subassembly S is 1 0 0 units in wekk 7 . Each unit of S requires 1 unit of T and 2

The demand cor subassembly S is 100 units in wekk 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V,2 units of of W, and 1 unit of X. Finally, each unit of U requires 2 units Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S,1 week to make T a component of S. The 20 units of U are needed for maintenanxe purposes. These units are needed in week 6. Additonally, a new order has been received for 80 units of S due in week 8. Modify the net requirements plan to reflect these changes.