Question: The demand for subassembly S is 1 1 0 units in week 7 . Each unit of S requires 2 units of T and 2
The demand for subassembly S is units in week Each unit of S requires units of T and units of U Each unit of T requires unit of V unit of W and units of X Finally, each unit of U requires units of Y and units of Z One firm manufactures all items. It takes weeks to make S week to make T weeks to make U week to make V weeks to make WIn addition to units of S there is also a demand for units of U which is a component of S The units of U are needed for maintenance purposes. These units are needed in week Modify the gross material requirements plan to reflect this change, weeks to make X weeks to make Y and weeks to make Z