Question: - = The demand for subassembly S is 1 3 0 units in week 7 . Each unit of S requires 2 units of T

-=The demand for subassembly S is 130 units in week 7. Each unit of S requires 2 units of T and 2 units of U. Each unit of T requires 1 unitnothing of V,2 units of W, and 2 units of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S,1 weeknothing to make T,2 weeks to make U,2 weeks to make V,3 weeks to make W,1 weeknothing to make X,2 weeks to make Y, and 1 weeknothing to make Z.
LOADING... Click the icon to view the product structure and the time-phased product structure.
LOADING... Click the icon to view the on-hand inventory.
Part 2
Suppose that in addition to 130 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for 80 units of S due in week 8. Modify the net material requirements plan to reflect these changes.
Part 3
Construct a new net material requirements plan (enter your responses as whole numbers).
Item
Week
Lead Time
1
2
3
4
5
6
7
8
(weeks)
S
Gross req
enter your response here
enter your response here
2
On hand
enter your response here
enter your response here
Net req
enter your response here
enter your response here
Order receipt
enter your response here
enter your response here
Order release
enter your response here
enter your response hereItem
On-Hand Inventory
Item
On-Hand Inventory
S
20
W
25
T
20
X
30
U
40
Y
40
V
30
Z
540
 -=The demand for subassembly S is 130 units in week 7.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!