Question: The demand for subassembly S is 1 4 0 units in week 7 . Each unit of S requires 2 units of T and 1

The demand for subassembly S is 140 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T
requires 1 unit of V,2 units of W, and 2 units of x. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm
manufactures all items. It takes 2 weeks to make S,1 week to make T,2 weeks to make U,2 weeks to make V,3 weeks
to make W,1 week to make x,2 weeks to make Y, and 2 weeks to make Z.
Click the icon to view the product structure and the time-phased product structure.
In addition to 140 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are
needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to
reflect this change (type 0 if the input box is not used).
 The demand for subassembly S is 140 units in week 7.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!