Question: The demand for subassembly S is 1 4 0 units in week 7 . Each unit of S requires 2 units of T and 2
The demand for subassembly is units in week Each unit of requires units of T and units of Each unit of requires units of units of and unit of Finally, each unit of requires units of and units of One firm manufactures all items. It takes weeks to make week to make T weeks to make week to make weeks to make weeks to make weeks to make and weeks to make
Click the icon to view the product structure and the timephased product structure.
Construct a gross material requirements plan type if the input box is not used
tableItemWeek,Lead Time weeksS Gross req,,,,,,,,Order release,,,,,,,,T Gross req,,,,,,,,Order release,,,,,,,,u Gross req,,,,,,,,Order release,,,,,,,,v Gross req,,,,,,,,Order release,,,,,,,,W Gross req,,,,,,,,Order release,,,,,,,,X Gross req,,,,,,,,Order release,,,,,,,,Y Gross req,,,,,,,,Order release,,,,,,,,z Gross req,,,,,,,,Order release,,,,,,,,
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock