Question: The demand for subassembly S is 100 units. Each unit of S requires 1 unit of T and 2 units of U. Each unit of

The demand for subassembly S is 100 units. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z.

Construct a gross material requirement plan.