Question: The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 unit s of

The demand for subassembly S is 100 units in week 7. Each unit of S requires
1
unit
of T and
2
units
of U. Each unit of T requires
1
unit
of V,
2
units
of W, and
1
unit
of X. Finally, each unit of U requires
2
units
of Y and
3
units of Z. One firm manufactures all items. It takes 2 weeks to make S,
1
week
to make T, 2 weeks to make U,
2
weeks
to make V,
3
weeks to make W,
1
week
to make X, 2 weeks to make Y, and
1
week
to make Z.
LOADING...
Click the icon to view the product structure and the time-phased product structure.
Part 2
In addition to 100 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used).
The demand for subassembly S is 100 units in week
Week 4 Lead Time (weeks) Item 1 2 N 3 4 5 6 7 S Gross req Order release 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!