Question: The demand for subassembly S is 100 units in week 7. Each unit of S requires 2 units of T and 2 units of U.

The demand for subassembly S is 100 units in week 7. Each unit of S requires

2

units

of T and

2

units

of U. Each unit of T requires

2

units

of V,

1

unit

of W, and

2

units

of X. Finally, each unit of U requires

2

units

of Y and

3

units of Z. One firm manufactures all items. It takes 2 weeks to make S,

2

weeks

to make T, 2 weeks to make U,

1

week

to make V,

2

weeks to make W,

1

week

to make X, 2 weeks to make Y, and

1

week

to make Z.

Part 2

a) Choose the correct product structure.

A.

2

1

0

S

T(2)

U(2)

Y(2)

Z(3)

V(2)

W(1)

X(2)

Level

A tree diagram has three levels 0, 1, and 2. At level 0, letter S is displayed. Then, S has two branches T (2) and U (2) at level 1. T (2) has three branches V (2), W (1), and X (2) at level 2. U (2) has two branches Y (2) and Z (3) at level 2.

B.

2

1

0

S

V(2)

U(2)

Y(2)

Z(3)

T(2)

W(1)

X(2)

Level

A tree diagram has three levels 0, 1, and 2. At level 0, letter S is displayed. Then, S has two branches V (2) and U (2) at level 1. V (2) has three branches, labeled T (2), W (1), and X (2) at level 2.UT (2) has two branches, lebeled Y (2) and Z (3) at level 2.

C.

2

1

0

S

T(2)

V(2)

U(2)

Z(3)

Y(2)

W(1)

X(2)

Level

A tree diagram has three levels 0, 1, and 2. At level 0, letter S is displayed. Then, S has two branches T (2) and V (2) at level 1. T (2) has three branches, labeled Y (2), W (1), and X (2) at level 2. V (2) has two branches, lebeled U (2) and Z (3) at level 2.

D.

2

1

0

S

U(2)

T(2)

W(1)

X(2)

V(2)

Y(2)

Z(3)

Level

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!