Question: The demand for subassembly ( S ) is 150 units in week 7 . Each unit of ( S ) requires 2 units of (
The demand for subassembly \( S \) is 150 units in week 7 . Each unit of \( S \) requires 2 units of \( T \) and 1 unit of U. Each unit of \( T \) requires 2 units of \( V, 1 \) unit of \( W \), and 2