Question: The demand for subassembly S is 150 units in week 7 . Each unit of S requires 1 unit of T and 1 unit of
The demand for subassembly S is 150 units in week 7 . Each unit of S requires 1 unit of T and 1 unit of U . Each unit of T requires 1 unit of V,1 unit of W , and 2 units of x . Finally, each unit of U