Question: The demand for subassembly S is 8 0 units in week 7 . Each unit of S requires 1 unitnothing of T and 2 units

The demand for subassembly S is 80 units in week 7. Each unit of S requires 1 unitnothing of T and 2 units of U. Each unit of T requires 1 unitnothing of V,2 units of W, and 2 units of X. Finally, each unit of U requires 1 unitnothing of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S,1 weeknothing to make T,2 weeks to make U,1 weeknothing to make V,3 weeks to make W,2 weeks to make X,2 weeks to make Y, and 2 weeks to make Z.
LOADING... Click the icon to view the product structure and the time-phased product structure.
Part 2
In addition to 80 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used).
Week
Lead Time
Item
1
2
3
4
5
6
7
(weeks)
S
Gross req
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
Order release
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
2make W,2 weeks to make x,2 weeks to make Y, and 2 weeks to make Z.
Click the icon to view the product structure and the time-phased product structure
 The demand for subassembly S is 80 units in week 7.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!