Question: The demand for subassembly S is 80 units in week 7. Each unit of S requires 2 units of T and 2 units of U.
The demand for subassembly S is
80
units in week 7. Each unit of S requires
2
units
of T and
2
units
of U. Each unit of T requires
2
units
of V,
1
unit
of W, and
2
units
of X. Finally, each unit of U requires
1
unit
of Y and
3
units of Z. One firm manufactures all items. It takes 2 weeks to make S,
2
weeks
to make T, 2 weeks to make U,
1
week
to make V,
2
weeks to make W,
2
weeks
to make X, 2 weeks to make Y, and
2
weeks
to make Z.
LOADING...
Click the icon to view the product structure and the time-phased product structure.
Part 2
Construct a gross material requirements plan (type 0 if the input box is not used).
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock