Question: The demand for subassembly S is 90 units in week 7. Each unit of S requires1 unit of T and 2 units of U. Each
The demand for subassembly S is 90 units in week 7. Each unit of S requires1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X.Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 2 weeks to make T, 2 weeks to make U, 1 week to make V, 2 weeks to make W, 1 week to make X, 2 weeks to make Y, and 2 weeks to make Z.
LOADING...
Click the icon to view the product structure and the time-phased product structure.
In addition to
90
units of S, there is also a demand for
30
units of U, which is a component of S. The
30
units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used).
| Week | Lead Time | ||||||||
| Item | 1 | 2 | 3 | 4 | 5 | 6 | 7 | (weeks) | |
| S | Gross req | nothing | nothing | nothing | nothing | nothing | nothing | nothing | |
| Order release | nothing | nothing | nothing | nothing | nothing | nothing | nothing | 2 | |
| T | Gross req | nothing | nothing | nothing | nothing | nothing | nothing | nothing | |
| Order release | nothing | nothing | nothing | nothing | nothing | nothing | nothing | 2 |
| U | Gross req | nothing | nothing | nothing | nothing | nothing | nothing | nothing | |
| Order release | nothing | nothing | nothing | nothing | nothing | nothing | nothing | 2 |
| V | Gross req | nothing | nothing | nothing | nothing | nothing | nothing | nothing | |
| Order release | nothing | nothing | nothing | nothing | nothing | nothing | nothing | 1 |
| W | Gross req | nothing | nothing | nothing | nothing | nothing | nothing | nothing | |
| Order release | nothing | nothing | nothing | nothing | nothing | nothing | nothing | 2 |
| X | Gross req | nothing | nothing | nothing | nothing | nothing | nothing | nothing | |
| Order release | nothing | nothing | nothing | nothing | nothing | nothing | nothing | 1 |
| Y | Gross req | nothing | nothing | nothing | nothing | nothing | nothing | nothing | |
| Order release | nothing | nothing | nothing | nothing | nothing | nothing | nothing | 2 |
| Z | Gross req | nothing | nothing | nothing | nothing | nothing | nothing | nothing | |
| Order release | nothing | nothing | nothing | nothing | nothing | nothing | nothing | 2 |