Question: The demand for subassembly S is 90 units in week 7. Each unit of S requires 1 unit of T and 2 units of U.

The demand for subassembly S is

90

units in week 7. Each unit of S requires

1

unit

of T and

2

units

of U. Each unit of T requires

1

unit

of V,

2

units

of W, and

2

units

of X. Finally, each unit of U requires

1

unit

of Y and

3

units of Z. One firm manufactures all items. It takes 2 weeks to make S,

1

week

to make T, 2 weeks to make U,

2

weeks

to make V,

3

weeks to make W,

1

week

to make X, 2 weeks to make Y, and

1

week

to make Z.

LOADING...

Click the icon to view the product structure and the time-phased product structure.

LOADING...

Click the icon to view the on-hand inventory.

Suppose that in addition to

90

units of S, there is also a demand for

30

units of U, which is a component of S. The

30

units of U are needed for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for

90

units of S due in week 8. Modify the net material requirements plan to reflect these changes.

Construct a new net material requirements plan

(enter

your responses as whole

numbers).

Item

Week

Lead Time

1

2

3

4

5

6

7

8

(weeks)

S

Gross req

enter your response here

enter your response here

2

On hand

enter your response here

enter your response here

Net req

enter your response here

enter your response here

Order receipt

enter your response here

enter your response here

Order release

enter your response here

enter your response here

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!