Question: The demand for subassembly Ss 130 units in week 7. Each unit of requires 2 units of Tandt unit of U. Each unit of requires
The demand for subassembly Ss 130 units in week 7. Each unit of requires 2 units of Tandt unit of U. Each unit of requires 2 units of V. 1 unit of W. and 1 unt of X Finally, each unit of Urequires 1 unit of Yand 2 units of Z. One om manufactures all. It takes 2 weeks to make 3, 2 weeks to make T. 2 weeks to make U. 1 week to make 2 weeks to make W. 2 weeks to make X 2 weeks to make Y and 2 weeks to make Click the loon to view the product rutture and the time-phased product structure Construct a grans material requirements plan type of the input box is not used). Week Lead Time Item 2 3 5 0 7 Grosse Order release IN LI 2 The demand for subassembly Ss 130 units in week 7. Each unit of requires 2 units of Tandt unit of U. Each unit of requires 2 units of V. 1 unit of W. and 1 unt of X Finally, each unit of Urequires 1 unit of Yand 2 units of Z. One om manufactures all. It takes 2 weeks to make 3, 2 weeks to make T. 2 weeks to make U. 1 week to make 2 weeks to make W. 2 weeks to make X 2 weeks to make Y and 2 weeks to make Click the loon to view the product rutture and the time-phased product structure Construct a grans material requirements plan type of the input box is not used). Week Lead Time Item 2 3 5 0 7 Grosse Order release IN LI 2
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts