The design of a hospital project is implemented. Some of the information on the activities is shown
Fantastic news! We've Found the answer you've been seeking!
Question:
The design of a hospital project is implemented.
Some of the information on the activities is shown in the following table:
Activity | Days | Immediate predecessors | ||
a | m | b | ||
A | 8 | 10 | 12 | |
B | 6 | 7 | 9 | |
C | 3 | 3 | 4 | |
D | 10 | 20 | 30 | A |
E | 6 | 7 | 8 | C |
F | 9 | 10 | 11 | B, D |
G | 6 | 7 | 10 | B, D, E |
H | 14 | 15 | 16 | F |
a Construct a network for this problem.
b Determine the expected time for each activity.
c Determine the critical path.
d What is the probability the project will be completed in time if the deadline is set after the completion time of five days?
Related Book For
Applied Regression Analysis and Other Multivariable Methods
ISBN: 978-1285051086
5th edition
Authors: David G. Kleinbaum, Lawrence L. Kupper, Azhar Nizam, Eli S. Rosenberg
Posted Date: