Question: The detailed work breakdown structure should be at a level at which you can a . collect data on the actual costs and value of

The detailed work breakdown structure should be at a level at which you can
a. collect data on the actual costs and value of the work completed during the performance of the project.
b. present the project on a one-page report.
c. make changes without affecting the project's completion date.
d. finish all the tasks on a single day each