Question: The difference between actual and standard cost caused by the difference between the actual number of resource - units used and the standard number of

The difference between actual and standard cost caused by the difference between the actual number of resource-units used and the standard number of resource-units that should have been used for the output of the period is called the:
Multiple Choice
Controllable variance.
Master budget variance.
Flexible-budget variance.
Quantity (or efficiency or usage) variance.
Price variance.