Question: The difference between the upper specification and the lower specification for a process is 0.60. The standard deviation is 0.05. Based on the given information,
The difference between the upper specification and the lower specification for a process is 0.60. The standard deviation is 0.05. Based on the given information, the process capability ratio, Cp = enter your response here (round your response to two decimal places).
Based on the process capability ratio (Cp) for the given information, one can say that the process is
very much capable
not at all capable
barely capable
-------------------------to produce within the design specifications.