Question: The discount rate is at the botto. Project A 4%, Project B 17% Profitability index. Given the discount rate and the future cash flow of
The discount rate is at the botto. Project A 4%, Project B 17%
Profitability index. Given the discount rate and the future cash flow of each project listed in the following table, use the pl to determine which projects the company should accept. Data table What is the Pl of project A? (Round to two decimal places.) (Click on the following icon in order to copy its contents into a spreadsheet.) Cash Flow Year o Year 1 Year 2 Project A - $1,800,000 $100,000 $300,000 $500,000 $700,000 $900,000 4% Project B - $2,500,000 $1,250,000 $1,05 000 $850,000 $650,000 $450,000 17% Year 3 Year 4 Year 5 Discount rate