Question: The discounted payback method: _ _ _ _ _ _ _ _ Question 4 options: A ) considers the time value of money. B )
The discounted payback method:
Question options:
A
considers the time value of money.
B
discounts the cutoff point.
C
discounts the initial cost.
D
is preferred to the NPV method.
E
considers project risks.