Question: The distribution mgr. is considering using error addback for his DRP system. To evaluate its use, he complied data for 3 periods on a sample
The distribution mgr. is considering using error addback for his DRP system.
To evaluate its use, he complied data for 3 periods on a sample product, the initial DRP record is given here:

Part A
Develop the DRP record for period 2 if demand in Period 1 was 24.
Part B
Completed the same records using the error addback method.
Period 1 2 3 4 5 forecast Requirements 30 30 30 30 30 In Transit 60 Projected Available Balance 10 40 10 40 10 40 Planned Shipments 60 60 Q = 60, lead time = 1, Safety stock = 10