Question: The durations associated with each activity in a project are shown below, as well as the logical dependencies among the activities. table [ [

The durations associated with each activity in a project are shown below, as well as the logical dependencies among the activities.
\table[[Activity,Pred.,Duration,ES,EF,LS,LF,TF],[O,--,0,,,,,],[A,O,3,,,,,],[B,O,5,,,,,],[C,A,6,,,,,],[D,A,2,,,,,],[E,D,3,,,,,],[F,D,3,,,,,],[G,B,4,,,,,],[H,F,G,5,,,,,],[I,C,4,,,,,],[J,E,I,2,,,,,],[K,J,3,,,,,],[T,H,K,0,,,,,]]
a. Neatly draw the CPM network diagram.
b. Compute the early times, late times, and total floats for each activity, and identify the critical path.
c. What could activity O be in a typical construction project?
d. What could activity T be in a typical construction project?
The durations associated with each activity in a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!