Question: The earliest start time for an activity is equal to A. the largestLF of the immediate predecessors. B. the smallest EF of the immediate predecessors.
The earliest start time for an activity is equal to A. the largestLF of the immediate predecessors. B. the smallest EF of the immediate predecessors. C. the largest ES of the immediate predecessors. D. the smallest ES of the immediate predecessors. E. none of the above