Question: The e-commerce team is behind schedule on its project. The customer is considering terminating the project if it does not get back on track. The

The e-commerce team is behind schedule on its project. The customer is considering terminating the project if it does not get back on track. The team is considering assigning additional resources to activities on the critical path to shorten the project's schedule duration. This is an example of